1 August 2020

The active stage of construction of the solar station is 25.9 MW.

In August 2020, Gelios Capital began the active phase of construction of a modern renewable energy facility: SES Zaporozhye-C with a peak panel capacity of 25.9 MW. The amount of investment in the project is UAH 439 million. The commissioning of the facility is scheduled for October 2020.

The main indicators of the object:
Photovoltaic modules – Risen;
Inverters – HUAWEI;
Metal structures are made of Metinvest metal;
Electrical equipment – Siemens, EDS-Engineering, Odesakabel;
Contractors – EDS-Engineering
The size of the station is 38 hectares;
Connection to the network – 35 kV.